Case Study
Client : John D Wood & Co
Project : Occupied Hotel
Project Value : £ 210K
The project involved the rewire of all public areas within the hotel, close co-ordination with management and staff was essential as the hotel was fully occupied throughout the works.
The project was carried out in phases to minimise disruption and allow the client to maintain their required guest levels throughout the project.
Operatives had to be very aware of the environment in which they were working, the special health and safety risks associated with these situations and take a very sensitive and considerate approach.